Practice Guide · Infiltration Certificate

Infiltration Design Certificate NRW: What the Water Authority Checks in 2026

An infiltration design certificate per DWA-A 138-1 is the single most common cause of delays in the German building permit process — not because it is technically complex, but because many submissions contain routine errors that force the water authority to request revisions. This guide walks through what is expected in 2026 and which mistakes are avoidable.

Author: Alvaro Burgos Cifuentes, M.Sc.Last updated: January 2026

At a glance

  • The DWA-A 138-1 infiltration certificate (October 2024 edition) is a mandatory part of the building permit whenever an infiltration system is planned.
  • Governing legal basis in NRW: § 55 (2) WHG, § 44 LWG NRW, plus § 8 WHG for the water-rights permit.
  • Required inputs: kf-value (DIN 18130), highest groundwater level, KOSTRA-DWD location-specific rainfall data, dimensioned site plan, conformity declaration.
  • Most common rejection causes: missing KOSTRA data, undocumented kf-value, no groundwater level stated, missing AFS63 assessment for discharge.
  • Above 800 m² of sealed surface or for direct discharge, an additional pollutant-load certificate per DWA-A 102-2 is required.

1. Legal basis — why a certificate is required at all

At the federal level, § 55 (2) of the German Water Resources Act (WHG) requires rainwater to be infiltrated locally, trickle-discharged or routed directly into a surface water body, unless legal, technical, geological or topographical reasons prevent this. Connection to the combined sewer is explicitly subordinate.

In NRW, § 44 LWG concretises this requirement: rainwater shall be infiltrated locally to the extent that this is technically feasible and economically reasonable. Exemption from this obligation is only granted in justified individual cases — and must be substantiated.

The water-rights permit per § 8 WHG is issued on the basis of this certificate. Without it, the water authority does not approve — and therefore the building permit cannot be issued.

2. What the water authority actually checks in 2026

The review by NRW's regional water authorities follows a largely standardised pattern. Case handlers check six core points — and exactly these six are what a standard infiltration certificate must deliver:

Water authority review grid

  1. 1Location-specific KOSTRA-DWD 2020 rainfall data extract (T = 30 a, durations from 5 min to 72 h)
  2. 2kf-value from a geotechnical soil report per DIN 18130 — with multiple boreholes in heterogeneous subsoils
  3. 3Mean highest groundwater level (MHGW) with at least 1.5 m clearance to the infiltration system base
  4. 4Dimensioned site plan showing infiltration system, connection lines, and elevations
  5. 5Dimensioning calculation including storage-to-discharge ratio and emergency overflow concept
  6. 6Conformity declaration with DWA-A 138-1, plus signature and stamp of a registered engineer

3. The five most common rejection reasons

In over 90 % of cases where the water authority requests revisions, the issue is one of these five:

Where certificates fail

  1. 1Generic kf-value without a soil report — e.g. 'kf = 1·10⁻⁵ assumed' instead of a measured value. Not accepted.
  2. 2Missing KOSTRA data — dimensioning against generic figures ('15 l/(s·ha)') instead of KOSTRA statistics for the specific location.
  3. 3No groundwater level — without the MHGW, the required clearance to the system base cannot be substantiated. Always re-requested.
  4. 4Missing emission assessment for discharge — for sealed surfaces with elevated pollution loads (traffic areas, industrial) or direct discharge into water bodies, the AFS63 certificate per DWA-A 102-2 is often missing.
  5. 5Sketch instead of calculation — a contractor's site sketch without hydraulic dimensioning does not meet the formal requirements. The authority expects a calculated design.

4. Pre-submission checklist

Before submitting the infiltration certificate, verify these eight points. Each one has caused a rejection in practice:

Pre-submission check

  1. 1Geotechnical soil report on hand, explicitly stating the kf-value with measurement method (DIN 18130-1 or field test)?
  2. 2KOSTRA-DWD 2020 data extract for the exact location (8×8 km grid) attached?
  3. 3Highest groundwater level substantiated — either in the soil report or via the LANUV database?
  4. 4Site plan shows system geometry, connection lines, emergency overflow, and elevation marks?
  5. 5Dimensioning includes storage-to-discharge ratio and infiltration time as a function of layer thickness?
  6. 6Conformity declaration with DWA-A 138-1 attached and signed?
  7. 7Above 800 m² sealed surface or for discharge: additional pollutant-load certificate per DWA-A 102-2?
  8. 8Calculation carries the stamp and signature of an engineer registered with the Chamber of Engineers NRW?

5. What good engineering delivers beyond the minimum

A code-compliant certificate is the obligation — sound engineering is the value-add. Three points we include in every project, beyond what DWA-A 138-1 strictly demands:

Climate adaptation surcharge: The standard requires a safety factor for climate change — we document it explicitly with the applied value and rationale, so the authority can trace the robustness of the design.

Hybrid systems for borderline soils: When the kf-value is at the lower limit (around 5·10⁻⁶ m/s), we combine an infiltration swale with retention storage rather than operating the system right at its edge.

Emergency overflow with destination proof: Where the design storm is exceeded, we substantiate the ordered overflow into a defined receiving feature — not just 'overflow provided'.

Standards & sources

  • DWA-A 138-1Facilities for the infiltration of rainwater (October 2024)
  • DWA-A 102-2Rainwater discharges — emission-based assessment (December 2020)
  • DWA-M 179-1Dimensioning of decentralised treatment units (2025)
  • DIN 18130-1Determination of soil permeability coefficient
  • KOSTRA-DWD 2020Coordinated heavy-rainfall regionalisation of the German Weather Service
  • § 55 (2) WHGWater Resources Act — rainwater disposal obligation
  • § 44 LWG NRWState Water Act NRW — rainwater disposal

Need an infiltration certificate for your project?

Send us your site plan and soil report — you receive a binding fixed-price quote within 24 hours (weekdays): one number and one deadline, both binding from complete documentation.